Nirantara Jyoti Yojana – Phase II

Nirantara Jyoti Yojana – Phase II

Chamundeshwari

Linking of Nirantara Jyothi Yojana (NJY) feeders to rural DTC's of villages for providing continuous power supply to domestic/Commercial/Power Installations by construction of 41 Nos. of 11KV line, providing & erection of 25 & 63 KVA DTC's and construction of LT line in Maddur & Mandya Taluks.

RAPDRP – (TANGEDCO)

Execution of distribution strengthening works under RAPDRP (Part-B) in 9 towns of TANGEDCO in Coimbatore region on total turnkey basis.

Kaleswaram Lift Irrigation Scheme – Mydaram 400/11 kV GIS Sub-Station in Karimnagar District & 400kV Quad Moose DC Line f!rom Ramadugu 400kV Sub-station to Mydaram 400/11 kV GIS – 21 Kms on Total Turnkey Basis

400kV DC Line from Malkaram to Narsapur - 74 Kms for TSTRANSCO, Telangana

220 kV Switching station at Thimmajipet and associated 220kv Line on turnkey basis for TSTRANSCO, Telangana

220Kv LILO Line to Nagari SS from existing Renigunta - GD Nellore 220kV DC Line on turnkey basis & 220kV Substation at Nagari for APTRANSCO, Andhra Pradesh

Supply, Erection, Construction, Testing and Commissioning of 132/33kV Substation at Duvvur along with connected 132kV DC/SC Line, 2nd circuit stringing and 1 no. 132kV Proddutur SS in Kadapa District for APTRANSCO, Andhra Pradesh

Maha Infra Plan II - Nagpur division works under MSEDCL on turnkey basis (33 kV & 11 Kv XLPE Cable works, 33/11kV Substations) for MSEDCL, Maharashtra

Maha Infra Plan II - Barshi division works under MSEDCL on turnkey basis (33/11 kV Substations and Lines) for MSEDCL, Maharashtra

400KV(Quad) DC line from Bonapally - Chittoor 400KV S/S -96.806 KM with one no. E/W and 1No. OPGW on Turn Key Basis